ConcernedJackie Ruffin PittmanSep 8, 2026

Asked what environmental assessments have been done on the data center and when the results will be public.

Board of Commissioners - Sep 8, 2026 · 33:05 →
OpposedWilson MorrisonSep 8, 2026

Demanded an immediate halt to permitting and incentives until an independent environmental and economic impact study is done, citing water use, backup redundancy and wetlands concerns.

Board of Commissioners - Sep 8, 2026 · 35:41 →
ConcernedBilly EasonAug 25, 2026

A part-time Enfield resident and hunter for 57 years, he said past promises about buffers near his property weren't kept and cited AI research that data center hum can affect wildlife and pets within a half-mile to two miles.

Board of Commissioners - Aug 25, 2026 · 1:24:10 →
ConcernedValerie WilliamsAug 25, 2026

Raised questions about environmental resource impacts, health effects, energy and water consumption, habitat loss, and whether contingency plans exist if the project does not proceed as presented.

Board of Commissioners - Aug 25, 2026 · 1:28:39 →
NeutralAngela WhitakerAug 25, 2026

Said she was in agreement with what Enfield Mayor Robinson would say.

Board of Commissioners - Aug 25, 2026 · 1:34:30 →
NeutralCamille RobinsonAug 25, 2026

Said she agreed with whatever Mayor Robinson would say and wanted the project to move forward.

Board of Commissioners - Aug 25, 2026 · 1:35:31 →
NeutralJoquita PhillipsAug 25, 2026

Said she would agree with whatever Mayor Robinson said.

Board of Commissioners - Aug 25, 2026 · 1:36:20 →
NeutralShalita PittmanAug 25, 2026

Said she agreed with what Mayor Robinson would say.

Board of Commissioners - Aug 25, 2026 · 1:36:40 →
NeutralMorris KembleAug 25, 2026

Had nothing to say but agreed with Mayor Robinson.

Board of Commissioners - Aug 25, 2026 · 1:37:13 →
NeutralDamari HarrisAug 25, 2026

Said he agreed with Mayor Robinson.

Board of Commissioners - Aug 25, 2026 · 1:38:02 →
SupportiveEddie MurrayAug 25, 2026

Asked whether the 45-decibel design figure covered generators or just the data center, whether generators would be enclosed, and after supportive remarks said the $1.75 million revenue is about 3% of the county budget and equaled 900 new $200,000 homes.

Board of Commissioners - Aug 25, 2026 · 1:38:17 →
MixedLaura WardAug 25, 2026

Asked whether the project would lower or raise taxes; Chairman Bryant said on behalf of the board that taxes will not increase as a result. She also said she agreed with Mayor Robinson.

Board of Commissioners - Aug 25, 2026 · 1:44:11 →
NeutralLashonsa MitchellAug 25, 2026

Said she agreed with Mayor Robinson.

Board of Commissioners - Aug 25, 2026 · 1:45:56 →
OpposedJames MillsAug 25, 2026

Submitted 40 written questions, demanded to know who the company is and its track record, pressed on inaudible shock-wave impacts on people and animals, questioned EMC power claims, and said he was disappointed in the board's transparency.

Board of Commissioners - Aug 25, 2026 · 1:46:10 →
NeutralTommy BowserAug 25, 2026

Wanted to know what's in it for residents — whether tax money will reduce taxes or fund schools — and questioned how electricity costs could be kept separate; the EMC CEO explained metering and contracting.

Board of Commissioners - Aug 25, 2026 · 2:02:01 →
SupportiveTony BrownAug 25, 2026

A former county manager, he said he came with an open mind after seeing negative data center coverage, visited data centers in Virginia, and argued the added revenue helps avoid future property tax increases; recalled a South Hill manager's only complaint was how to spend the surplus.

Board of Commissioners - Aug 25, 2026 · 2:23:01 →
SupportivePatrick CrawlsAug 25, 2026

Supported the project from an economic standpoint, noting the ~$1.75 million revenue equals about a 3.5-cent tax rate relief, and asked about generator emissions and wildlife noise impacts.

Board of Commissioners - Aug 25, 2026 · 1:18:06 →